| 7 | || 1|| Do, 28. Feb || Introduction to the Orxonox project || || ETF B105, ETL F11 || |
| 8 | || 2|| Do, 06. Mar || Introduction to Modelling || || ETZ B105, ETL F11 || |
| 9 | || 3|| Do, 13. Mar || Introduction to Framework || || ETZ B105, ETL F11 || |
| 10 | || 4|| Do, 20. Mar || Start of implementation || || ETL F11 || |
| 11 | || 5|| Do, 27. Mar || || || ETL F11 || |
| 12 | || 6|| Do, 03. Apr || Review 1 || || ETL F11 || |
| 13 | || 7|| Do, 10. Apr || || || ETL F11 || |
| 14 | || 8|| Do, 17. Apr || Review 2, models complete || || ETL F11 || |
| 15 | || 9|| Do, 24. Apr || || || ETL F11 || |
| 16 | ||10|| Do, 08. May || Review 3 || || ETL F11 || |
| 17 | ||11|| Do, 15. May || All components/models finished. last merge || || ETL F11 || |
| 18 | ||12|| Do, 22. May || prepare Presentation || || ETL F11 || |
| 19 | ||13|| last week of May || Presentation || || ? || |