Project Work
Scenario
Topics
Difficulty:
++ | very advanced |
+ | advanced |
+- | moderate |
- | peace of cake |
Overview:
Difficulty | Ticket | Owner | Project Page | |
Framework | ||||
+ | ||||
+- | ||||
++ | ||||
Content Creation | ||||
Create a Spacegate | +- | |||
+ | ||||
++ |
Milestones
- 08.Nov 06: Choose the Project
- 22.Nov 06: Project Plan Review (1 week)
until now you have created on your project wiki-page: - 22.Nov 06: Start of Implementation and Content Creation (5 weeks)
- write header files
- write the source itself
- collect reference materials
- make outlines (skizzen) of the objects you like to create
- generate content
- 20.Dec 06: Implementation stop, review in teams and design resync (1day)
- show what you did, and how it will go on
- are you sill in your development schedule?
- 20.Dec 06: Continue implementation/ content creation (2 weeks)
- the source implementation will continue and finish as fast as possible
- the content created should be finished as soon as possible too.
- 10.Jan 07: Project freeze: debug, documentation and testing phase (1 week)
- use GDB
- use Valgrind
- document with doxygen
- write a module description on the wiki
- write a model/content description on the wiki
- 24.Jan 07: Code finished and working perfectly
- 31.Jan 07: Convention and big show